Main Rd/Wall Pl intersection

Main Rd-Wall Pl existing



Main Rd-Wall Pl proposed

Issues

Excessive delays are experienced by traffic exiting the Wall Pl precinct due to:

  • increased numbers of vehicles using Wall Pl
  • right turning vehicles exiting Wall Pl are holding up left turning vehicles
  • few gaps between vehicles using Main Rd

Considerations

Kenepuru Corridor

The aim is to provide continued safe access to all businesses and road users using the Kenepuru Corridor for now and in the future.

Main Rd/Wall Pl

  • no crashes have been reported within 30m of intersection 2015-2019
  • stakeholder feedback to date has been incorporated into the options

Proposal 

Add another approach lane.

Your feedback

Next steps

  • collate feeback
  • refine proposal
  • contact submitters re refined proposal
  • confirm proposal
  • tender/construction: June to October 2020 (subject to confirmation of funding)