Waitangirua and Te Ara Kāpehu link roads water and electricity upgrades
Porirua City Council, Wellington Electricity, Wellington Water and Kāinga Ora are teaming up to carry out critical infrastructure service upgrades along link roads, at the same time. These upgrades will increase resilience and supply for local residents and will benefit Porirua as a whole, but will cause traffic disruption during the work, with road and lane closures.
From Monday 13 January 2025, our contractors will be working across two intersections relating to the Waitangirua Link Road services upgrade work – the Warspite Avenue/Waitangirua Link Road intersection and the Navigation Drive/Schooner Drive intersection.
Warspite Ave works
Starting on Monday 13 January, work will start to lay the electricity ducting across the intersection and into Niagara St. We will also be laying the large watermain across the intersection to the connection point for the existing Warspite Ave watermain. This work involves carrying out pressure testing, disinfecting the pipes, and receiving sign-off from Wellington Water and then completing the connection itself.
Temporary reinstatements of the asphalt will be done as work progresses, and our crews will come back at the end to permanently reinstate the road surface. We expect work at this intersection to take about two months.
What to expect at this intersection:
Navigation Drive/Schooner Drive
This work involves the installation of two manholes on the grass verge adjacent to the existing pump station and also starts on 13 January.
What to expect:
Communication
We will be running public notices about this work in the 17 December and 14 January editions of Kapi-Mana News. We will also be posting on Antenno, our Facebook channel, and website alerts page. Letterbox drops will be distributed this week to affected local residents and businesses.
Progress on site and work over the holiday period
Work continues to progress well on the Waitangirua Link Road with over 700 metres of trenching, duct and water pipe laying completed, along with the basecourse reinstatement work.
Our team will be working through the Christmas shut down period, only taking a break on the statutory days.
If you have any questions, please contact us on [email protected]
The Waitangirua and Te Ara Kāpehu (Whitby) Link Roads Project started on 4 November 2024, and will take about seven months to complete both stages.
Stage 1 – Waitangirua Link Road – full closure from 4 November 2024
The first stage of the construction work has started, with the full closure of Waitangirua Link Road (from Warspite Avenue to the T-junction with Te Ara Kāpehu. This stage is expected to take up to five months to complete.
During the closure, drinking water pipes will be laid, along with cabling for electricity network upgrades.
While the road is closed, Council will also take the opportunity to remove wilding pine trees, clear vegetation and install signage for the increased speed limit on the Waitangirua Link Road, which is being raised to 60km/h as part of the Speed Management Plan for Porirua City.
Once the cabling and pipework is completed, the road will be fully resurfaced.
We encourage motorists to plan their journeys using alternative routes and allow extra time and appreciate everyone’s patience while this important work is carried out.
Work to lay drinking water pipes and electricity ducts along Waitangirua Link Road is well underway, with more than 250m of trenching, pipe and duct laying completed.
While some unexpected ground conditions and wet weather has slowed us down, the JFC contract team is making good progress and is currently reinstating the lower base layers of the trench.
Over the next few weeks, it will be more of the same with trenching, pipe and duct laying, and reinstating base layers as the team moves up the road.
The electronic vehicle message boards will be taken down over the next week or so and replaced with static project information boards.
If you have any questions please contact us on [email protected]
Stage 2 – Te Ara Kāpehu (formerly the Whitby) Link Road – partial closure
The second stage of work will take place along Te Ara Kāpehu Link Road (between the Silverbrooke development and the T-junction with Waitangirua Link Road) also to lay water pipes and power cabling. This work is scheduled to happen once the first stage is complete, and the Waitangirua Link Road is back open. The intention is that one lane will remain open, with traffic management measures in place for about two months.
During both closures, drinking water pipes will be laid, along with cabling for electricity network upgrades.
The new power cables will allow future capacity increases, anticipating housing growth as this area continues to expand.
An additional 2.4 km of drinking water pipes will connect to the new, larger reservoir being built at the end of Stemhead Lane.
The reservoir will cater for future demand on Porirua’s drinking water network and improve network resilience by adding a second connection to upper Whitby and providing capacity in case of an emergency. These upgrades also reduce and ultimately remove current reliance on pump stations.
The new reservoir is planned for construction in the first half of 2025 and will be delivered by Te Rā Nui. It will increase the amount of water available from 4.5 million litres to 13.5 million litres.
For the work to be completed as quickly and efficiently as possible, the decision has been made to fully close the road from 4 November 2024, so work crews have unimpeded access to the site. If we were to keep the road partially open the work would take considerably longer and cost considerably more.
At the time of building the Transmission Gully link roads, water and electricity infrastructure wasn’t installed because no one knew either the scale and/or timing of residential development and the new reservoir had not been planned. The eastern parts of Porirua have been growing quickly and the new reservoir is being built in 2025. We are working together with all parties using a ‘dig once’ approach to try and minimise disruption as much as possible.
Yes, road and lane closures will be disruptive for regular users of the link roads, and individuals and businesses living and operating in the area.
The level of disruption depends on where people are going, where they’re leaving from and what else is happening at the time. Our traffic modelling shows there may be some hotspots but they are likely to be minimal and only at peak times.
To keep disruption to a minimum, we are working together using a ‘dig once’ approach to get water and electricity upgrades done at the same time. Teaming up to do this infrastructure work means we only need to close the road once, rather than twice, which would have been more inconvenient to road users,
We encourage motorists to plan their journeys using alternative routes and allow extra time.
Yes, this is likely to be done in two stages and will mostly be chipseal. Stage one will be resurfacing the one lane where the road has been dug up to accommodate the new pipes and cables. Current areas of the road that are failing will be repaired. Stage two will happen a year later once this new surface has bedded in. Then the Council will come back and resurface both lanes of the road. Stage two will result in minimal disruption – likely just a few days of traffic management measures in place.
Warspite Avenue/Niagara Street intersection
From Monday 13 January 2025 we will be laying electricity ducting and water pipes in the Warspite Avenue/Niagara Street intersection.
This is a part of the Waitangirua Link Road works and will take about two months to complete.
What to expect:
Navigation Drive/Schooner Drive works
From Monday 13 January 2025 we will be installing two manholes on the grass verge adjacent to the existing pump station on Navigation Drive, Whitby.
This is a part of Te Ara Kāpehu Link Road (formerly known as the Whitby Link Road) works and will take about one month to complete.
What to expect:
Yes, you can download it here [jpg, 2MB].
Email [email protected]
If people are asking the same questions, we'll add them to our FAQs.
Email [email protected] and ask to be added to our mailing list.
Waitangirua Link Road closed from Monday for up to 5 months
Just a reminder that the Waitangirua Link Road will be closed from this coming Monday, 4 November, for up to five months. This will enable improved drinking water supply and electricity network services for the eastern Porirua suburbs and Whitby.
Porirua City, Wellington Water, Wellington Electricity and Kāinga Ora are working together to upgrade these essential services, with John Fillmore Contracting (JFC) undertaking the work.
We have been trying to make sure as many people as possible know about this work through Kapi Mana News, Facebook, RNZ, Sāmoa Capital Radio, posters, flyers, emails, letters, our Council website and through our Antenno app.
There are also roadside VMS (variable message sign) boards up in key locations to let people know about the work and Google maps will no longer show the route for the duration of the work.
Please feel free to forward this email on to anyone else who needs to know.
A recap on what’s happening
There will be a full closure of Waitangirua Link Road – from Warspite Ave to the T-junction with Te Ara Kāpehu (formerly the Whitby Link Road). The work is expected to take up to five months to complete.
During the closure, drinking water pipes will be laid, along with cabling for electricity network upgrades.
The road will be fully closed so work crews have full access to the site. Keeping the road partially open during the work would take longer and cost more. Once the cabling and pipework is completed, the road will be resurfaced.
People who normally use the road will need to plan their trip in advance and allow extra time to reach their destination.
Once the Waitangirua Link Road work is complete and is back open, there will be a partial (one-lane) closure of part of Te Ara Kāpehu Link Road, also to lay water pipes and power cabling.
The water pipes will connect to the new, larger reservoir to be built at the end of Stemhead Lane.